Roadway Construction Update

  • Concrete work within the Fox Pointe subdivision is 90% complete.  Soon City crews will start patching sections or roadway.  After patching microsurfacing will shttps://cityofsycamore.com/wp-content/uploads/2019/07/Street-Construction-Update-071019.pdftart in late July/ early August.  Additional notices will be distributed to impacted residents prior to the start of work.
  • Mill and overlay on Hathaway Drive, Fox Bend Drive, and northern Fox Pointe Drive is slated for late July.
  • Edward Street construction is scheduled to begin as early as the week of July 15th.

Please contact Mark Bushnell, City Engineer with any questions or comments.  He can be reached via email mbushnell@cityofsycamore.com or by phone at 815-895-4434. To view the complete schedule, please click HERE.