Street Maintenance Update – July 28, 2017

Street Maintenance Update – July 28, 2017

The contractor has focused on completing work on streets that were already under construction.  The final concrete work and the start of paving is planned for Mason Court, Albert Street, Esther Street, West Street and Meadow Lane.    The contractor has also started restoration work adjacent to concrete improvement.    The focus of roadway related work will remain on these streets before shifting to other areas.

A subcontractor will be completing water valve installation on Charles Street, Park Avenue and adjacent areas.  This work must be completed before roadway work, within these areas, which is anticipated to start in August.

The tentative schedule outlined above may change from time to time depending on weather conditions, availability of labor, materials and equipment, etc.    Please contact the City at 815-895-4557 if you require special accommodations.  Thank you for your patience as we work to improve the City’s infrastructure.

Click here to view the full street construction update.