Street Maintenance Update – August 25, 2017

Street Maintenance Update – August 25, 2017

The contractor is wrapping concrete work on Park Avenue, Charles, Edward, Waterman and Chauncey Streets.  Current work in this area also includes the replacement of driveways.

Milling operations have started on Loomis Street and Elmwood in preparation for asphalt paving.

Next week concrete crews will move to South Cross Street, Center Avenue and Stark Avenue.  Pavement milling is scheduled for the week of September 5th and will include streets where concrete work has occurred.  Paving operations will follow milling with a lag of approximately one week.

Please look for signs (Fresh Oil, No Parking, Road Construction Ahead, etc.)  for indication of the work being performed in each area.