Street Maintenance Update – August 18, 2017

Street Maintenance Update – August 18, 2017

Next week, the contractor will be focusing on completing concrete work.  This includes Park Avenue, Charles, Edward, Waterman and Chauncey Streets.  Once the concrete is complete, Curran will bring in their milling and paving machines.  This is tentatively scheduled for the week of August 28th.