Concrete work has begun on Mason Court and Loomis Street.  This will be followed by the excavation of the street.

The contractor will then move to the West Street/ Albert Avenue and Esther Avenue area before transitioning to Meadow Lane.

The Motor Fuel Tax (MFT Project) will start next week.  This includes construction on Pebblewood Drive, Bayberry Lane and Locust Street.

The tentative schedule outlined above may change from time to time depending on weather conditions, availability of labor, materials and equipment, etc.    Please contact the City at 815-895-4557 if you require special accommodations.  Thank you for your patience as we work to improve the City’s infrastructure.