Construction Update – June 21, 2016

Construction Update for June 21, 2016

Work will continue on City streets over the next three to four weeks.

During the week of June 27th the contractor will be milling pavement on Ottawa St (Main to Walnut St), Somonauk St (Il Rt 64 through Elm St) and Parking Lot 2.

Paving on all remaining streets is tentatively scheduled for the week of July 4th. This includes the previous streets as well as Lucas Street and Mason Court.    Manhole adjustments and restoration will occur during mid July.

Please understand that all work is weather dependent and subject to the contractor’s ability to procure the necessary materials.

Please follow all traffic control signs and exercise care when traveling in construction zones.