7/27/18 Weekly Construction Update

7/27/18 Weekly Construction Update:  Paving has started.

The Contractor has paved Exchange Street and it is open to traffic

Milling was completed on Sycamore, Borden, Woodgate, and Maertz.

The same streets are now being prepped for stone base and paving.

  • Utility work will begin on Washington Place on Monday July 30th with roadway work following.
  • The Bethany Road Repair is half complete.

The tentative schedule outlined above may change from time to time depending on weather conditions, availability of labor, materials and equipment, etc.   To view the entire schedule CLICK HERE.  Please contact the City at 815-895-4557 if you require special accommodations.   Thank you for your patience as we work to improve the City’s infrastructure.