6/29/18 Weekly Construction Update:  A recent break in the weather allowed work to progress during the later part of the week.

 

  • William Charles Construction paved the first layer of asphalt on Coltonville Road.
  • Exchange Street concrete work is complete.
  • Locust Street concrete work is 90% complete.
  • Washington Street concrete work is underway.
  • Concrete work on Woodgate Drive, Sycamore Street, and Borden Avenue is approximately 50% complete.
  • Work will continue during the week of July 2nd.

The tentative schedule outlined (to view click HERE) may change from time to time depending on weather conditions, availability of labor, materials and equipment, etc.