6/15/18 Weekly Construction Update

6/15/18 Weekly Construction Update

Weather has delayed or postponed most of Friday’s work.  William Charles Construction has rescheduled Bethany Road paving for Monday June 18th.

Curran Contracting and their subcontractor will continue work on Exchange Street and Locust Street.  Work will then transition to Washington Ave.  Concrete scheduled for removal on Woodgate Drive, Sycamore Street, and Borden Avenue will be sawcut.   The tentative schedule outlined above may change from time to time depending on weather conditions, availability of labor, materials and equipment, etc.  To view the entire schedule, CLICK HERE.

Please contact the City at 815-895-4557 if you require special accommodations.   Thank you for your patience as we work to improve the City’s infrastructure.